Renovations at Bealey’s
As you may have noticed, things are changing at Bealey’s and will take about 3 months for the construction to be complete. This will be done in stages allowing us to remain open during the process.
Stage 1
9th August – 31st August – Renovations of the function room and old reception area begin, not to much disruption to our normal restaurant and bar however we apologies for the noise during the day.
Stage 2
1 October – Our main restaurant and bar close, during this time we will be getting a new roof, a new kitchen and as a tidy up in the bar and restaurant. We will be operating out of the function room each day from 4.30pm with a limited menu. Our other bars are operating as per normal and we are happy to take you to either of these in our courtesy vans if required.
Grand re-opening
Keep an eye out early November for our grand reopening! During this time you will also have the opportunity to walk through the new accommodation